Grid Extension Project in Hes-i-Awal Kohistan District of Kapisa Province

11 August, 2021

A grid extension project is ongoing with approximately 50% physical progress in Maqsud Khel village of Hes-i-Awal Kohistan district, Kapisa province under the Community Support Program of CASA-1000 (CASA-CSP).

Maqsud Khel village, which is located in Hes-i-Awal Kohistan district, is one of the villages located on the CASA-1000 project corridor

....More

Publish Date: 11 Aug 2021

Three Development Projects Ongoing in Boz Khord CDC at Value of Nearly AFN 4.5m

August 02, 2021

The construction of 180-meters-long protection wall, three water-intakes and an irrigation canal project is ongoing in Boz Khord Community Development Council in the Capital of Kunduz province through the Community Support Program of CASA-1000 (CASA-CSP) under the umbrella of the Ministry of Rural Rehabilitation and Development (MRRD).

With 70 % physical progress to date, the

....More

Publish Date: 02 Aug 2021

Construction of 1500m Long Irrigation Canal in Kapisa

July 27, 2021

The construction of an irrigation canal project is ongoing in Nejrab district of Kapisa province through the Community Support Program of CASA-1000 (CASA-CSP) under the umbrella of the Ministry of Rural Rehabilitation and Development (MRRD).

With a 60 percent physical progress, the 1500 meters long and 1.3 meter high irrigation canal project

....More

Publish Date: 27 Jul 2021

Panjshir Governor Assures Comprehensive Support to CASA Project

The Governor of Panjshir met with local government officials to address the social barriers lie ahead of CASA-1000 project and assured comprehensive support to the project.

The Governor of Panjshir Kamaluddin Nezami met with Panjshir Breshna Acting Head Sayed Hussain Yousufi and the Provincial Office Head of Citizens' Charter National Priority Program (CCNPP), discussing the social obstacles in CASA-1000 project.

The Governor listened to social

....More

Publish Date: 17 Jul 2021

Construction of 20 Culverts and a Retaining Wall Ongoing in Kunduz

July 11, 2021

Construction of a retaining wall together with 20 culverts is ongoing by the Ministry of Rural Rehabilitation and Development under the CASA-1000 Community Support Program (CASA-CSP) in Qara Turukman Community Development Council, Imam Saheb district, Kunduz province.

With a 70 percent physical progress, the 61 meters long and five meters high retaining wall will be completed at

....More

Publish Date: 11 Jul 2021

Construction of 860m Long Irrigation Canal Underway in Laghman

The construction of an irrigation canal project is ongoing in Qal-e-Wazir village of Qarghaee district of Laghman province through the Community Support Program of CASA-1000 (CASA-CSP) under the umbrella of the Ministry of Rural Rehabilitation and Development (MRRD).

The 860 meters long and 60cm high irrigation canal project is being implemented through the Community Development Council (CDC) under CASA-CSP to gain support of the people for

....More

Publish Date: 08 Jul 2021

CASA-1000 Technical Code Meeting held in Bishkek

The CASA-1000 Technical Code Working Group Meeting took place on June 28 to July 03, 2021 in Bishkek, the capital city of Kyrgyz Republic.

The meeting was attended in-person by representatives of the Islamic Republic of Afghanistan, the Kyrgyz Republic, the Islamic Republic of Pakistan, and the representative of the Republic of Tajikistan attended by videoconference (VC).

24 June 2021,

A three-day training program was held for newly recruited engineers of CASA-1000 Community Support Program (CASA-CSP).

The training was conducted in the conference hall of the Citizens’ Charter National Priority Program of the Ministry of Rural Rehabilitation and Development (CCNPP/MRRD) to start the work of the new component (CSP-MCCGs) of CASA-1000 Community Support Program (CASA-CSP).

20, June 2021

The construction of a protection wall project is ongoing in Shergar Community Development Council (CDC), Kama district of Nangarhar province through the CASA-1000 Community Support Program (CASA-CSP) under the umbrella of the Ministry of Rural Rehabilitation and Development (MRRD).

At a tune of over AFN 5 million and 175 thousand, the 710 meters long protection wall project is being

....More

Publish Date: 22 Jun 2021

Grid Extension Project in Laghman

12 June, 2021

A grid extension project is ongoing with 62% physical progress in Fazal Muhammad village of Qarghaee district, Laghman province under the Community Support Program of CASA-1000 (CASA-CSP).

Fazal Mohammad village, which is located a few kilometers from Mehtarlam, the capital of Laghman province in Qarghahi district, is one of the villages located on the CASA-1000

....More

Publish Date: 12 Jun 2021

Construction of Irrigation Canal Ongoing in Laghman

6 June, 2021

The construction of an irrigation canal project is ongoing in Masha Khail village of Mehterlam, the capital city of Laghman province. This project with 43 % physical progress to date, is underway through the Community Support Program of CASA-1000 (CASA-CSP).

The 1100 meters long irrigation canal project is being implemented through the Community Development Council

....More

Publish Date: 06 Jun 2021

Governor of Kapisa: We Will Resolve Social Problems Lie Ahead CASA-1000

2 June, 2021,

Abdul Latif Murad, Governor of Kapisa, visited Hesa Awal Kohistan district to address the social issues of CASA-1000 project and strengthen social cohesion and public’s trust on the project in the district.

A joint meeting chaired by Abdul Latif Murad was held between the provincial authorities, CASA-1000 Project Team Members and local communities on May 31, 2021,

....More

Publish Date: 02 Jun 2021

Kapisa Governor meets CASA-1000 Project Officials

31 May 2021,

In this meeting, which was also attended by Engineer Aziz-ur-Rehman Afzali Alokozai, Mayor of Kapisa’s capital Mahmoud Raqi and Qazi Ahmad Ahmadi, Head of Kapisa Green Trend, officials and staff of the CASA-1000 project, while presenting a report on the activities, functions and progress of the CASA-1000 project in the areas of Kuhband ha district, discussed some social problems with the governor of Kapisa province.

Abdul Latif

....More

Publish Date: 01 Jun 2021

A meeting held in Panjshir to address social challenges lie ahead CASA-1000

31 May 2021,

A meeting was held in Panjshir under the chairmanship of Engineer Kamaluddin Nezami, Governor of Panjshir, to address the social challenges of implementing the CASA 1000 project, with the presence of Ms. Rahela Atai, Deputy Governor in Social and Economic Affairs.

In this meeting, the challenges in several districts of the province were discussed with the presence of representatives of Kabul Breshna, Rokha and Anaba district governors,

....More

Publish Date: 01 Jun 2021

Construction of Protection Wall Underway in Laghman

23, May 2021

The construction of a protection wall project is ongoing in Soor Sangian village of Qarghaee district, Laghman province. This project with 66 % physical progress to date, is underway through the Community Support Program of CASA-1000 (CASA-CSP).

The 270 meters long protection wall project is being implemented through the Community Development Council (CDC) under CASA-CSP to gain support of the

....More

Publish Date: 23 May 2021

Rehabilitation of Canal Project through CASA-CSP in Nangarhar

26 April, 2021

The rehabilitation of an irrigation canal project is ongoing in Sher Gar Jalal village of Kama district, Nangarhar province. This project is underway through the Community Support Program of CASA-1000 (CASA-CSP).

The irrigation canal is being implemented through the Community Development Council (CDC) under CASA-CSP to gain support of the people for the successful implementation

....More

Publish Date: 26 Apr 2021

Kunduz Governor Visits CASA-1000 Project Construction Site

Governor of Kunduz province Mr. Abdul Satar Mirzakwal visits construction site of CASa-1000 poles installation on 7th March 2021.

The governor was accompanied by several local authorities during the visit from construction site and CASA-1000 progress in the mentioned province.

During the meeting with the representatives of the CASA-1000 implementing companies Mr. Mirzakwal said that he will be always available to assist the implementation of the project to the extent possible.

....More

Publish Date: 25 Apr 2021

CASA-1000 Electricity Towers Installation Starts in Kapisa

CASA-1000 Electricity Poles installation was recently started in Kapisa province. Overall, installation process of the towers for CASA-1000 electricity transmission and trade project is well under way in Kapisa Province.

This is to be noted that CASA-1000 passes through seven provinces in Afghanistan such as Kunduz, Baghlan, Panjshir, Kapisa, Kabul, Laghman and Nangarhar.

....More

Publish Date: 25 Apr 2021

Construction of Canal Project Underway in Laghman

The construction work of an irrigation canal project is ongoing in Qal-e-Makal village of Qarghaee district, Laghman province. This project is underway through the Community Support Program of CASA-1000 (CASA-CSP).

The irrigation canal with the length of 750 meters and 0.6 meters wide is being implemented through the Community Development Council (CDC). The project has paved the ground for community residents to gain access to employment opportunities.

....More

Publish Date: 25 Apr 2021